This project included 120KW on one elementary school, 11,000 SF of elevated structure, 18 T structures and was a DSA project. The complete project for Solar City includes four school districts statewide, twenty-one schools and over 6.7 megawatts.
Build Group self-performed the 123 concrete piers and 32,200 LF of gauge steel purlins. In order to provide the best costs to our clients, Build Group purchases the steel material directly from the mill. This also gives us better control of the product as it is fabricated and delivered to the jobsites. The project requires complex logistics and scheduling management to ensure every rebar cage, steel column and purlin were delivered on time and per the stringent DSA specifications.